On Monday (13/01/2014) we released an outline of our set roadmap, today as promised we will be releasing a timeline with dates on each aspect of the development process. This shows our commitment to transparency and gives a better idea on what exact stage we are on at all times. As we go through multiple developmental stages in parallel, we will be releasing regular detailed updates on our progress. Our next updates will be consistent developmental updates on what is being worked on and what has been achieved.

Timeline:

Project Start: 16/08/13

Project Finish: 15/07/14

 

Task Name

Duration

Start

Finish

    Viper ASIC Miner Project

238 days

Tue 16/08/13

Tue 15/07/14

Scrypt Core and Chip Architecture

15 days

Mon 06/01/14

Fri 24/01/14

System Architecture

5 days

Mon 06/01/14

Fri 10/01/14

FPGA Implementation and Testing

131 days

Tue 16/08/13

Fri 14/02/14

ASIC Development

85 days

Mon 20/01/14

Fri 16/05/14

Viper Miner Board Design

95 days

Mon 13/01/14

Fri 23/05/14

Viper Miner Firmware Development & Testing

118 days

Wed 01/01/14

Fri 13/06/14

Mechanical, Thermal & Misc

69 days

Mon 13/01/14

Thu 17/04/14

System Assembly & Testing

2 days

Mon 16/06/14

Tue 17/06/14

System Integration & Testing

20 days

Wed 18/06/14

Tue 15/07/14

User Manual

12 days

Fri 18/04/14

Mon 05/05/14

 

Roadmap (recap):

 

Alpha Technology team 

To unsubscribe

newsletter

No virus found in this message.
Checked by AVG - www.avg.com
Version: 2014.0.4259 / Virus Database: 3681/7006 - Release Date: 01/15/14